The installation and commissioning of marine Loading Arms for the Pipelines and Product Marketing Company (PPMC) involved engineering design and fabrication of loading arms. It also covered isolation and flushing of the suction and delivery lines to the obsolete loading arms. Additionally, it involved the removal of the old foundation housing the existing loading arms and carting away the demolished spoils, installation of hold bolts, down bolts and cast with grade 30 concrete; installation of loading arms, painting of all the pipes on the platform to the metering unit, calibration and set- ting up of the system for commissioning, commissioning, training, supervision and handing over of the unit.
Mr. Obinna Odum, Operations Manager, Bell Oil & Gas (standing) during a Classroom Training for Pipelines and Product Marketing Company (PPMC) personnel.
Cross section of PPMC Personnel during a Practical Training Session at the Calabar Jetty