A team of skilled BOG engineers embarked on the Glassfiber Reinforced Epoxy (GRE) shut-down pipe installation and repair project in March on the ERHA Floating, Production, Storage, and Offloading (FPSO) facility.
The BOG GRE team is reputed for providing technological solutions to many corrosion challenges faced in several multifaceted projects, especially in the Nigerian Oil and gas industry.
ExxonMobil’s ERHA (FPSO) facility has a liquid storage capacity of 2.2 million barrels.
The work scope included the repair and installation of a 40″ header line connecting to a 20″ line using a 40×20″ reducing Tee fitting. After the completion of the project, the team witnessed a successful functional testing of the line.
Due to the team’s outstanding performance, the client referred the team to another Exxon Mobil facility to carry out more GRE repairs.
The repaired fitting undergoing the curing process