BOG personnel carrying out final finishes on a ready to be installed spool at the FPSO
On the 5th of Feb 2021, six BOG Personnel were mobilized to embark on a Glassfiber Reinforced Epoxy (GRE) pipe repair project on Agbami FPSO.
Agbami Floating, Production, Storage and Offloading (FPSO) was built in 2007. It features an overall storage capacity of 2.15 million barrels of crude oil. It can handle 450 million cubic feet of gas production and 450,000 barrels of injected water a day.
As a leading player in the GRE space with an experienced team of personnel, BOG successfully executed the repair of an 8” x ¾” bushing saddle leak, 18” x 4” Reducing flanged leak, Leaking 14” Tee, and the arrangement of MINOX 2.
The repairs will provide corrosion protection and prolong the lifecycle of the FPSO.
BOG personnel reconditioning a used flanged